Guadalupe River Project
This project included construction of a two-track railroad bridge and associated approaches, a vehicular bridge, a pedestrian undercrossing, a maintenance road and environmental restoration features along the Guadalupe River between the former UPRR Bridge No. 3 and UPRR Bridge No. 4 in San Jose, California. Bridge construction necessitated that the environmentally sensitive Guadalupe River flows be diverted. The railroad bridge was constructed in phases to allow active train traffic to continue during the entire construction duration.
Location
San Jose, CA
Contract No.
W91238-09-C-0015
Start Date
August 2009
Completion Date
October 2011
240 calendar days
Original Contract
$3,312,150
Final Amount
$3,416,587
Owner
Department of the Army
US Army Corps of Engineers
2100 Bridgeway, Sausalito, CA 94965
Donald Hough
415-289-3301
Engineer
Corps of Engineers, Sacramento District
1325 J Street, Room 1480, Sacramento, CA 95814
San Jose, CA
Contract No.
W91238-09-C-0015
Start Date
August 2009
Completion Date
October 2011
240 calendar days
Original Contract
$3,312,150
Final Amount
$3,416,587
Owner
Department of the Army
US Army Corps of Engineers
2100 Bridgeway, Sausalito, CA 94965
Donald Hough
415-289-3301
Engineer
Corps of Engineers, Sacramento District
1325 J Street, Room 1480, Sacramento, CA 95814