San Francisco International Airport Electrical Power Distribution Improvement System
PrōVen constructed a new electrical substation, electrical and telecommunications duct banks, as well as electrical cables and equipment. PrōVen also completed excavation and backfilling, utility trenches, locating existing utilities, removal of 12kV existing cable and furnishing and installing new metal clad switchgreat and 12kV electrical cables. PrōVen successfully managed the project despite specific challenges with air traffic volume and special security activities. Project Management required daily coordination with the Airport Duty Manager to accommodate air traffic volume and access to restricted areas.
Location
San Francisco International Airport
San Francisco, CA
Contract No.
3828 B & C
Start Date
January 2007
Completion Date
February 2009
Original Contract
$10,916,339
Final Amount
$11,025,247
Owner
San Francisco International Airport
Airport Commission
676 . McDonnell Road, San Francisco, CA 94128
Rudy Alegre
650-821-7818
San Francisco International Airport
San Francisco, CA
Contract No.
3828 B & C
Start Date
January 2007
Completion Date
February 2009
Original Contract
$10,916,339
Final Amount
$11,025,247
Owner
San Francisco International Airport
Airport Commission
676 . McDonnell Road, San Francisco, CA 94128
Rudy Alegre
650-821-7818