PrōVen installed 5,000 LF of 24" diameter restrained pipe, connected it to the existing pipe at the intersection of Villa Vista Drive and Yerba Buena Road. PrōVen also installed 820 LF of 12" diameter pipe and portable water service assemblies with vaults and valves, 600 LF of 18" diameter pipe, and two 18" recycled water service assemblies at the reservoir site. Two 137' diameter, 2.75 MG pre-stressed concrete tanks were also constructed as well as 3,600 LF of access road leading to the reservoir site.
Location
3745 Old Yerba Buena Road, San Jose, CA
Contract No.
1955-36
Start Date
June 2005
Completion Date
November 2006
360 working days
Original Contract
$9,384,040
Final Amount
$9,365,465
Owner
City of San Jose
Transportation and Developmental Services
200 East Santa Clara Street, 7th Floor, San Jose, CA 95113
Richard Yau
408-255-8686
[email protected]
Engineer
Brown and Caldwell
201 North Civic Drive, Suite 115, Walnut Creek, CA 94596
3745 Old Yerba Buena Road, San Jose, CA
Contract No.
1955-36
Start Date
June 2005
Completion Date
November 2006
360 working days
Original Contract
$9,384,040
Final Amount
$9,365,465
Owner
City of San Jose
Transportation and Developmental Services
200 East Santa Clara Street, 7th Floor, San Jose, CA 95113
Richard Yau
408-255-8686
[email protected]
Engineer
Brown and Caldwell
201 North Civic Drive, Suite 115, Walnut Creek, CA 94596